SpaceX Names Proposed Arizona Data Center Colossus 3
On November 27, SpaceX’s proposed data center campus in southeastern Arizona had a name: Colossus 3. Elon Musk announced it on social media before county officials have voted on the application. SpaceX says the 750-acre campus would be among the world’s most advanced AI training facilities and create 1,000 jobs.
Cochise County Faces a High-Stakes Vote on SpaceX’s Power-Hungry Campus
On November 27, SpaceX publicized the name Colossus 3 for its planned 750-acre AI campus in Cochise County, even though local approval is still pending. The county’s Planning and Zoning Commission is scheduled to vote on December 9, after Attorney General Kris Mayes asked for a delay because, she argued, major questions about the project remain unresolved.
The proposed campus would need up to 6 gigawatts of electricity, and SpaceX says it would rely on gas turbines until the local utility can supply the requested power. The site is near Willcox Playa, where protected sandhill cranes migrate. In Mississippi, SpaceX has faced scrutiny over turbines operating without federal air permits, while residents have complained of noise and emissions.
SpaceX says it will use treated wastewater, fund $3.6 billion in grid upgrades and bring 1,000 jobs. But those promises do not erase the need for careful review of a project with potentially major demands on local power and the environment. County staff have questioned the attorney general’s authority to seek a delay and drafted a sharply critical response. State utility and environmental agencies must also review parts of the plan.
Arizona Officials Should Let SpaceX’s Data Center Face the Established Process
On November 27, SpaceX announced Colossus 3, the name for its proposed $50 billion, 750-acre AI campus in Cochise County. The county’s Planning and Zoning Commission is expected to vote on December 9, but Attorney General Kris Mayes has urged officials to put off the decision over concerns about water, electricity, noise and the environment.
SpaceX says it has followed the county’s process, consulting nearby residents and public officials. It has also pledged to pay $3.6 billion for grid upgrades, use treated wastewater and bring 1,000 jobs to the area. Those commitments deserve consideration as commissioners assess the application, rather than having the decision preempted by political pressure.
County staff have questioned Mayes’ authority to ask for a delay and prepared a draft response defending the local review process. The project would still require reviews by state utility and environmental agencies, and its energy agreements need state approval. Those steps provide additional scrutiny without discarding the county’s scheduled vote. SpaceX says the campus would initially use gas turbines while the local utility works toward supplying the requested 6 gigawatts.