City Orders Demolition of Damaged Flatbush Building
On November 18, New York City’s Department of Buildings ordered the demolition of 1323 Flatbush Ave., saying engineers found the Brooklyn apartment building too unstable to repair safely. It was badly damaged when 1321 Flatbush Ave. collapsed on November 11, killing eight people and injuring 20 others.
The department said the damaged structure has worsened as weather reached its exposed interior. Installing the supports needed to stabilize it would require workers to enter unsafe areas, officials said. Unstable floors and asbestos contamination also mean tenants cannot return to retrieve their belongings.
Before demolition work begins, city contractors plan to shore up the neighboring property at 1325 Flatbush Ave. The city has set up a fenced safety zone, and full vacate orders remain in place for nearby properties. Displaced tenants are receiving hotel accommodation arranged by city officials and the American Red Cross until November ends.
The collapse’s cause remains under investigation. The buildings department is inspecting more than 160 construction sites linked to companies and individuals associated with the adjacent development. It is also investigating six developers connected to the project at 2625 Bedford Ave., where excavation plans had been approved in March. A contractor inspection report had noted cracking on the north side of 1321 Flatbush Ave.; construction was halted that month.
Flatbush Demolition Follows Fatal Collapse and Warning Signs
A fatal collapse has left nearby tenants unable to return home, and the city now says the damaged building at 1323 Flatbush Ave. must be demolished. The Department of Buildings said on November 18 that the structure had become too unstable to repair safely after 1321 Flatbush Ave. fell on November 11.
The tragedy raises urgent questions about safeguards around the excavation project next door. Plans for work at 2625 Bedford Ave. were approved in March, and a contractor inspection report recorded cracking on the north facade of the building that later collapsed. Construction was halted that month, while the cause of the collapse remains under investigation.
City officials say workers could be endangered if they entered 1323 Flatbush Ave. to install stabilizing supports. Floors are unstable, asbestos contamination prevents tenants from collecting belongings, and weather has worsened the building’s condition. Contractors must reinforce 1325 Flatbush Ave. before demolition begins.
The city is examining more than 160 construction sites connected to companies and individuals involved in the development, while investigating six developers tied to the project. Displaced residents are being housed with city assistance and help from the American Red Cross until November concludes. The investigation must establish how the collapse happened and whether oversight failed to prevent it.
City Moves to Demolish Unsafe Building After Brooklyn Collapse
The city is taking steps to prevent another injury after the November 11 collapse at 1321 Flatbush Ave. damaged the adjoining building. On November 18, the Department of Buildings ordered 1323 Flatbush Ave. demolished, concluding that repairs would put workers at risk.
Officials say the structure has continued to deteriorate as its interior is exposed to weather. Unstable floors and asbestos contamination also make it unsafe for former residents to enter and collect their possessions. Before demolition crews start, contractors will reinforce the nearby property at 1325 Flatbush Ave.
The decision puts immediate safety first while the cause of the collapse remains under investigation. The city has established a fenced safety zone, and people forced from their homes are staying in hotels arranged by the city and Red Cross aid, at least until November ends.
The Department of Buildings is inspecting more than 160 construction sites connected to people and companies involved in the adjacent development, and is investigating six developers tied to the project at 2625 Bedford Ave. Excavation plans there were approved in March, and a contractor report noted cracking on the north facade of 1321 Flatbush Ave. Construction was halted that month. Investigators are still determining what caused the collapse.
Reported by Gothamist, New York Post, ABC7 New York, CBS New York, Daily Mail US, amNY, ABC7 Los Angeles, Fox News, AZFamily.