Puerto Rico Supreme Court Orders Luma Contract Canceled
On November 25, Puerto Rico’s Supreme Court issued a 5-4 ruling in favor of ending the government’s contract with Luma Energy. The decision leaves open who will take over the company’s work as outages persist and crews continue repairing the grid damaged by Hurricane Maria in 2017.
Luma took over electricity transmission and distribution in June 2021 under a multimillion-dollar agreement. It inherited infrastructure described as crumbling after decades of neglect and mismanagement by the Puerto Rico Electric Power Authority. Luma said it disagreed with the court’s decision, would respect the judicial process and was considering its legal options. It also raised concern about the ruling’s potential effect on work to strengthen and modernize the grid.
The government sued the company nearly a year ago, following Gov. Jenniffer González’s campaign pledge to cancel the contract. González said in December 2025 that Luma had nearly $11 billion in federal funds available for rebuilding but had recovered about $550 million in reimbursements from FEMA. At the time officials brought their case, she argued that improvements had not come at the pace or with the consistency Puerto Rico deserved.
The government and Luma have an operations and maintenance agreement, plus a supplemental deal tied to the Electric Power Authority’s debt restructuring. Both were due to expire in November 2022, but the government extended the supplemental agreement by letter. González has argued that the extension gave Luma indefinite control and violated the law and sound public administration. Dissenting justices warned of potentially major consequences from ending the contract, while another criticized the ruling as catering to the governor. Power cuts have also been attributed to Genera PR, which oversees power generation.
Court Ruling Challenges Luma’s Grip on Puerto Rico’s Power System
On November 25, Puerto Rico’s Supreme Court ruled 5-4 in favor of canceling Luma Energy’s contract, putting the island’s power operator under a cloud as outages continue. The decision brings a long-running fight over who controls an essential public service to a turning point, but leaves the next operator unresolved.
Gov. Jenniffer González had campaigned on ending the contract, and her government sued Luma nearly a year ago. She has argued that an extension letter gave the company indefinite control in violation of law and sound public administration. The court’s decision advances that challenge, though dissenting justices warned that ending the deal could have monumental consequences.
Luma took over transmission and distribution in June 2021, inheriting a deteriorated system after decades of neglect and mismanagement by the Puerto Rico Electric Power Authority. González said the company had nearly $11 billion in federal funds available for rebuilding by December 2025, but had recovered only about $550 million in FEMA reimbursements. She also said the system had not improved with the speed and consistency Puerto Rico deserved.
Luma disputes the ruling and says it is weighing legal options, while warning that the decision could affect grid modernization and public safety. The two agreements with Luma include an operations and maintenance deal and a supplemental agreement linked to the authority’s unfinished debt restructuring. Both were due to expire in November 2022, but the supplemental deal was extended. The court’s ruling now raises an urgent question: who will manage the grid while repairs continue and blackouts persist? Power cuts have also been attributed to Genera PR, the private company overseeing generation.
Court’s Luma Ruling Risks More Uncertainty for Puerto Rico’s Grid
On November 25, Puerto Rico’s Supreme Court voted 5-4 to cancel the government’s contract with Luma Energy, a decision that risks adding uncertainty to an island already struggling with outages. The ruling leaves unanswered who will take over transmission and distribution while crews continue repairing damage from Hurricane Maria.
The contract is not simply a political target: Luma assumed responsibility in June 2021 for a grid that had deteriorated through decades of neglect and poor management by the public Electric Power Authority. Luma says the ruling could affect efforts to strengthen and modernize the system, and it is evaluating legal options. Dissenting justices also warned that the consequences of termination could be monumental.
González’s government sued after she pledged during her campaign to cancel the agreement. She has criticized Luma’s performance and argued that an extension letter gave the company indefinite control unlawfully. But the government’s challenge does not itself answer how service will be maintained or who will take over the work.
The arrangement includes an operations and maintenance agreement and a supplemental deal connected to the authority’s debt restructuring. Both were set to expire in November 2022; the government extended the supplemental agreement by letter, and the authority remains mired in restructuring. González said in December 2025 that Luma had nearly $11 billion in federal funds available for grid rebuilding but had recovered about $550 million in FEMA reimbursements. With outages continuing—and Genera PR also blamed for some of them—the court’s decision makes the transition and reliability of service the immediate stakes.
Reported by KPRC 2 Click2Houston, WTOP.