Arizona AG Seeks Delay on SpaceX Data Center Vote
Arizona Attorney General Kris Mayes is urging Cochise County to delay its planned December 9 vote on a special-use permit for SpaceX’s proposed $50 billion data center near Willcox. In a letter to county officials, she said state and federal agencies need more time to examine the project’s potential effects before local approval moves forward.
The proposed campus would cover about 750 acres and require 1.5 gigawatts of power when it opens, rising to 6 gigawatts at full buildout. Mayes’s letter says the company plans to invest $3.6 billion in grid upgrades, yet has not explained how it would address a 4.5-gigawatt gap at full capacity.
The letter also raises concerns about water use, fire response, traffic, wildlife and possible effects on military electronic testing. Although the campus is planned to use dry cooling and the application estimates its own water use at 7 to 10 acre-feet annually, Mayes says that figure excludes water needed to generate its electricity. The site is next to Willcox Playa, where Sandhill Cranes winter, and would include about 6,150 Tesla Megapack batteries.
If supervisors proceed with the vote, Mayes recommends delaying the permit’s effect and withholding building permits until required state and federal approvals are obtained. She also wants the county to review the full project rather than separate phases, and to require more public meetings. Mayes plans to hold a town hall on December 3 at Cochise Elementary School. The county vote is scheduled for December 9.
Delay SpaceX Approval Until Its Costs Are Examined
Cochise County should not approve SpaceX’s proposed $50 billion data center before officials and residents have answers about its demands on power, water and public services. Arizona Attorney General Kris Mayes is asking the county to delay its December 9 permit vote so state and federal agencies can study the project.
The proposed 750-acre campus would start at 1.5 gigawatts of power demand and reach 6 gigawatts. Mayes says SpaceX intends to spend $3.6 billion on grid upgrades, yet has not explained how it would cover the 4.5-gigawatt difference at full buildout. That scale makes a complete review essential before local approval, rather than allowing the project to grow through separate applications.
The stakes extend beyond electricity. The site lies in the Willcox Active Management Area, designated to curb groundwater depletion, and next to Willcox Playa, where Sandhill Cranes winter. The application estimates the dry-cooled campus would use 7 to 10 acre-feet of water annually, but Mayes says that does not include water used to produce its power. Her letter also flags fire-response needs for about 6,150 batteries and traffic impacts from construction.
Mayes recommends that any permit remain ineffective and building permits be withheld until required approvals are secured. She also calls for a full-project review and additional public meetings. She plans a December 3 town hall; the county vote is set for December 9.
County Should Demand Answers Before Backing SpaceX Project
A project of this scale should not move ahead on promises and incomplete details. Arizona Attorney General Kris Mayes is urging Cochise County to postpone its December 9 decision on SpaceX’s proposed $50 billion data center until state and federal agencies have examined its potential impacts.
SpaceX’s planned campus would cover about 750 acres and require 6 gigawatts of power at full buildout. Mayes’s letter says the company has proposed $3.6 billion in grid investments but has not explained how it would close a 4.5-gigawatt gap. The county should insist on a review of the entire project, rather than allow its effects to be considered in piecemeal phases.
Mayes also points to practical local concerns: the project’s power generation could require water beyond the campus’s stated use, construction could increase heavy traffic on rural roads, and about 6,150 batteries could pose challenges for responders because the site is outside a fire district. The planned site borders Willcox Playa, where Sandhill Cranes winter, and the letter says the military may need to assess possible interference with electronic testing near Fort Huachuca.
If county supervisors vote anyway, Mayes recommends delaying the permit’s effective date and withholding building permits until relevant state and federal authorizations are in place. She also seeks more public meetings. A town hall is planned for December 3, ahead of the county’s December 9 vote.